Project Cost Estimates
(click on line item to see details)
Naira
USD
Satellite Equipment and Connection Fees
83,608,000
836,080
Expansion and Redundancy
5,634,000
56,340
Capacity Building
1,633,800
16,338
TOTALS:
N90,875,800
$908,758